Monday 26 June 2017

Website upgrade

We're pleased to say we have now gone live with our new website which has a fresh look and simpler navigation:



Shortly we'll also update the website with our new projects from spring / summer this year - it has been a very busy time for us with many varied projects going up!

Friday 14 April 2017

Weyhill project certified as Passivhaus Plus!

Our Weyhill project has now officially been certified as meeting the new Passivhaus Plus standard - we are one of the first 3 houses in the country to reach this new standard. The Plus standard has the Passivhaus very demanding minimal energy requirements to heat the building, aswell as the house also producing as much energy as it consumes.

Being Passivhaus, the building fabric requires minimal heating, and the heating system is very efficient. The little energy required for the building is equal to the energy produced on site by the large 10kWp PV roof  mounted PV system.

Our clients Ben and Elle are rightly very proud of their achievement in reaching the new plus standard:
We look forward to building more Passivhaus, Passivhaus Plus, and Passivhaus Premium homes in the future - which are set to become a mandatory EU requirement after 2021.


Monday 13 March 2017

Hennerwood passivhaus drone footage

Whilst erecting our Hennerwood farm passivhaus project we produced drone footage of the timber frame. Please take a look at the footage of this stunning building in the Herefordshire countryside!





Monday 6 February 2017

Chief's Farm Cottage Passivhaus

We have just finished the erection of our Chief's Farm Cottage project in Essex. For this project Touchwood designed and installed the strip foundation with our special thermally bridge free detail, to create a very thermally efficient slab suitable for passivhaus. The image below shows the 300mm EPS insulation installed:


Following the powerfloat finished concrete slab on top of the EPS, we then installed the pre-cut timber frame, with our robust air tight board installed over the external surface. Unusually, this build has the airtight layer going under the roof structure, rather than having the roof warm side - our usual approach. This improved the surface area to volume ratio for passivhaus PHPP analysis, and avoids the client heating space that is not used - they didn't require vaulted ceilings in the upstairs rooms. See below some images of the timber frame:



We are now commencing install of the MVHR duct work, simply installed in the-cut holes, prior to hand over to the clients tradesman for the follow on works.

See below an image of the pre-cut duct routes in the frame. The MVHR system is modelled for acoustic performance, with silencers in the network as necessary. This unique integrated approach to MVHR and frame design allows all ducts to be within the floor cassette, where they do not need boxing out, and will have the space around them filled with Warmcel, creating near silent running,


We look forward to the project being finished and being added to our list of passivhaus certified homes.